APPALACHIAN POWER COMPANY
SMITH MOUNTAIN PROJECT NO. 2210
ILP - PROCESS PLAN
       
RESPONSIBLE LICENSE APPLICATION PRE-FILING    
ENTITY SCHEDULE MILESTONES DATE REGULATION
       
APCO Commence consultations with participants and public 11/13/2002 5.1(d)
APCO Begin PAD preparation 11/13/2002 5.6
APCO Request for Section 106 consultation authorization 7/10/2003 5.5(e)
FERC Designation as non-federal representative for Section 106 11/4/2003 5.5(e)
  consultation    
APCO File NOI and PAD 11/1/2004 5.5,5.6
APCO Issue public notice of NOI and PAD 11/1/2004 5.3(d)(2)
FERC Tribal Consultation 12/1/2004 5.7
FERC Notice of Commencement of Proceeding and Issue of 12/31/2004 5.8
  Scoping Document No. 1 (SD1)    
FERC Site Visit and Scoping Meetings 1/26 & 1/27/2005 5.8(d)
Participants Comments on PAD/SD1, and information gathering 3/1/2005 5.9(a)(b)
  and study requests  
FERC Scoping Document No. 2 (SD2) issued (If necessary) 4/15/2005 5.1
APCO Proposed study plan filed 4/15/2005 5.11
APCO w/participants Proposed study plan initial meeting 5/15/2005 5.11
Participants Comments on proposed study plan 7/14/2005 5.12
APCO File revised study plan 8/13/2005 5.13(a)
Participants Comments on revised study plan 8/28/2005 5.13(b)
FERC Study plan determination issued 9/12/2005 5.13(c)
Federal agencies w/ Filing of study dispute notice 10/2/2005 5.14(a)
mandatory condition    
authority    
Dispute Resolution Dispute resolution panel convened 10/22/2005 5.14(d)
Panel      
APCO Comments and information regarding dispute filed 10/27/2005 5.14(i)
Dispute Resolution Findings of panel filed 11/21/2005 5.14(k)
Panel    
FERC Study dispute determination issued 12/11/2005 5.14(l)
APCO Conduct studies and gather information - first season 2005 & 2006 5.15
APCO Initial study report 9/12/2006 5.15(c)(1)
APCO Initial study report meeting 9/27/2006 5.15(c)(2)
APCO Meeting summary & study plan modifications (If necessary) 10/12/2006 5.15(c)(3)
Participants Comments on meeting summary 11/11/2006 5.15(c)(4)
APCO Response to meeting summary comments 12/11/2006 5.15(c)(5)
FERC Disagreement resolution & revisions ot study plan 1/10/2007 5.15(c)(6)
APCO Conduct studies and gather information (If needed) 2007 5.15
APCO Updated study report & Notice of Intent to file a Draft 9/12/2007 5.15(f)
  License Application (if so selected)  
APCO Updated study report meeting 9/27/2007 5.15(f)
APCO Updated study report meeting summary 10/12/2007 5.15(f)
APCO File Preliminary Licensing Proposal or Draft License 11/2/2007 5.16(a)(b)
  Application  
APCO File application for 401 Certification from VDEQ 11/2/2007 5.22
Participants Comments on meeting summary 11/11/2007 5.15(f)
APCO Response to meeting summary comments 12/11/2007 5.15(f)
FERC Disagreement resolution 1/10/2008 5.15(f)
FERC/Participants Comments on Preliminary Licensing Proposal or Draft 1/31/2008 5.16(e)
  License Application  
APCO File Application for New License 3/31/2008 5.17(a)