| APPALACHIAN POWER COMPANY | |||
| SMITH MOUNTAIN PROJECT NO. 2210 | |||
| ILP - PROCESS PLAN | |||
| RESPONSIBLE | LICENSE APPLICATION POST-FILING | ||
| ENTITY | SCHEDULE MILESTONES | DATE | REGULATION |
| APCO | Notice of filing of application in local newspapers | 4/14/2008 | 5.17(d)(2) |
| FERC | Notice of filing of application by the Commission | 4/14/2008 | 5.19(a) |
| FERC | Determination on outstanding Additional Study Requests & | 4/30/2008 | 5.19(d),5.20(a) |
| notification of application deficiencies | |||
| FERC | Notice of application accepted and ready for environmental | 5/30/2008 | 5.22 |
| analysis | |||
| Participants | Comments, protests, interventions, recommendations, and | 7/29/2008 | 5.23(a) |
| preliminary terms and conditions or fishway prescriptions | |||
| filed | |||
| APCO & Participants | Reply comments due | 9/12/2008 | 5.23(a) |
| VDEQ | 401 Certification Issued | 11/2/2008 | 5.23(b)(2) |
| FERC | EA issued for comment if draft NEPA document not | 1/10/2009 | 5.24(a) |
| required | |||
| APCO & Participants | Comments on EA due | 2/24/2009 | 5.24(c) |
| APCO & Participants | Modified mandatory prescriptions or terms and conditions | 4/25/2009 | 5.24(d) |
| filed | |||
| USFWS | ESA consultations and biological opinion | 5/24/2009 | N/A |
| FERC | License issued (Single EA) | 6/24/2009 | FPA |
| The following schedule will be followed if Commission staff determine that a draft and final environmental | |||
| document is necessary: | |||
| FERC | Draft EA or EIS issued for comment | 3/9/2009 | 5.25(a) |
| APCO & Participants | Comments on Draft EA or EIS due | 4/25/2009 | 5.25(c) |
| APCO & Participants | Modified mandatory prescriptions or terms and conditions | 6/24/2009 | 5.25(d) |
| filed | |||
| USFWS | ESA consultations and biological opinion | 7/22/2009 | N/A |
| FERC | Final environmental document issued | 9/22/2009 | 5.25(e) |
| FERC | License issued | 11/21/2009 | FPA |