SMITH MOUNTAIN
PROJECT NO. 2210
SHORELINE
MANAGEMENT PLAN
STEERING COMMITTEE
MEETING
JUNE 19, 2001
NOTES
On June 19, 2001 at 11:00 a.m. (EDT), the individuals listed below met at the Bedford County Administrative Building located in Bedford, Virginia to discuss the development of the Shoreline Management Plan (SMP) for the Smith Mountain Project. The meeting represented the second meeting of the Steering Committee for developing the Shoreline Management Plan.
Name Representing
Kirby Richardson Bedford County, Virginia
Gina DeSantis Bedford County, Virginia
Mike Davidson Campbell County, Virginia
Patrick Lawrence Franklin County, Virginia
Greg Sides Pittsylvania County, Virginia
Steve Campbell Association of Lake
Area Communities (ALAC)
Dave Banta Smith Mountain Lake Association (SMLA)
Ron Willard, II Smith Mountain Lake Chamber of Commerce/Partnership (SMLCC/P)
Richard Gibbons Virginia Dept. of Conservation and Recreation (VDCR)
Brian Heft VDCR
Mike McLeod Virginia Dept. of Environmental Quality (VDEQ)
Mike Scanlan VDEQ
Charlie Sledd Virginia Dept. of Game and Inland Fisheries (VDGIF)
Dan Wilson VDGIF
Bob Clark Virginia Department of Health (VDH)
Mrs. Bob Clark VDH
Heather Campbell Federal Energy Regulatory Commission (FERC)
John Estep FERC
Shana High FERC
Mike Thacker American Electric Power (AEP)
Teresa Rogers AEP
Liz Parcell AEP
Frank Simms AEP
A representative from the Virginia Department of Historic Resources (VDHR) was asked to attend, however there was no representation at the meeting. The U.S. Fish and Wildlife Service (FWS) indicated that they will not provide representation at the Steering Committee meetings. AEP will continue to keep them informed with committee information.
The meeting consisted of presentations by the representatives from AEP with questions and comments provided by the members of the Steering Committee and representatives for the Federal Energy Regulatory Commission. Following is a synopsis of the presentations made and items discussed at the June 19 meeting.
·
Mr. Simms outlined the
meeting objectives which were identified to include: (1) addressing the
comments received since the last meeting; (2) obtaining FERC comments; (3)
finalizing the scope of work; (4) addressing any outstanding issues; and (5)
discussing the schedule.
·
Referencing Section 5.3
- Shoreline Erosion, Mr. Simms explained that environmentally sensitive areas
such as wetlands would be identified.
If such wetlands are upstream in the back of a residential cove, it
would be up to the committee to decide, giving due consideration to
environmental concerns and permit requirements, whether or not dredging should
be allowed. Mr. Banta indicated that
the SMLA is interested in developing rough estimates of sediment loads into the
lake. Mr. Simms noted that such a project could be considered under relicensing
but not as part of the SMP.
·
There were no changes
proposed to Section 5.4 - Environmental and Natural Resources. Mr. McLeod questioned if the data would be
available in digital format. Mr. Simms
responded that the consultant would make mapping recommendations and digital
formats considered.
·
Referencing Section 5.5
- Cultural Resources, Mrs. Campbell questioned if Native American groups were
identified as having any project interests.
She indicated that new regulations require that the interests of Native
American groups be considered and addressed.
Mr. Gibbons explained that there could be such interests below Leesville
Lake. The Scope of Work of work will be
modified to include Native American interests.
·
Referencing Section 5.8
Consultations and Public Meetings, Mr. Simms noted that there should be one
more steering committee meeting prior to the first public meeting. The purpose of that meeting would be to give
the selected Consultant the opportunity to become familiar with the members of
the Committee. It was asked that
members of the Steering Committee begin thinking about possible locations,
publicity efforts, etc… for the initial public meeting. Mr. Clark questioned if four public meetings
would be adequate. Mr. Simms responded
that it may not be but additional meetings can be held if necessary. It was further explained that four meetings
are referenced in the Scope of Work document to establish a base number for the
bidders to develop their proposals. Mr.
Gibbons questioned the purpose of the public meetings. Mr. Simms responded that the meetings would
be designed to inform the public of what is going on as well as to listen and
obtain information from those who know the lake best. The members of the Steering Committee estimated that there could
be as many as 250 to 300 attendees at the public meetings. Regarding public meetings, the Consultant
will be responsible for scheduling and determining the locations for the public
meetings including the first public meeting.
·
Mr. Gibbons asked about
the bidding process and potential consultants.
Mr. Simms identified those on the list.
Mr. Gibbons suggested that the team include a good landscape architect.
·
Mr. Wilson questioned
how conflict resolution would be handled.
Mr. Simms responded that it would be handled by the Steering
Committee. Mr. Simms further explained
that when AEP submits the final SMP to the FERC, there should be signatures
from each agency, local government, and non-governmental organization
represented on the Steering Committee to acknowledge that they agree in
principal with the SMP as filed with the FERC.
Therefore, whoever represents those agencies and groups as part of the
Steering Committee must be in a position to keep their respective agency, etc…
informed and be able to have the any associated agreement signed without
modification at the appropriate time.
He added that should any of the agencies, counties or non-governmental
organizations want additional presentations regarding development of the SMP,
AEP would be glad to do so.
·
Referencing Section 6.1
- Work Schedule, Mr. Lawrence asked if the 6/30/03 date shown on the schedule
as the end of the work includes FERC review and approval. Mr. Simms stated that the date represents
the filing date with the FERC. Mr.
Simms noted that we are ahead of schedule by 30 days and the bid process is
approximately a 45-day process. When
questioned about the amount of time required to obtain FERC approval of the
SMP, Mr. Estep responded that 6 months would be ambitious especially
considering the type of plan to be filed.
·
Mr. Simms highlighted
future activities including the consultant bid and selection process, public
meetings, data collection and field verification, preparation of the SMP, and
FERC filings. He asked if anyone from
the Steering Committee would be interested in attending the pre-bid
meeting. Upon discussion, it was agreed
that representation from the Steering Committee was not necessary.
·
Mr. Campbell
specifically requested that an explanation of why the plan would not be
addressing water levels be included in the minutes. Mr. Simms responded that the SMP would be based upon existing
license conditions. Water levels and
how the project is operated is beyond the scope of the SMP. Addressing water levels would require that
potential impacts on individuals and the environment downstream of the Smith
Mountain Project would need to be assessed.
Any modifications would then require a license amendment. The SMP is intended to address the
management of the shoreline. Water
levels would be more appropriately addressed as part of the effort to relicense
the Smith Mountain Project.
·
If the Consultants
selected to submit proposals happen to submit proposals that are very close, an
additional meeting of the Steering Committee could be called at which the
Consultants would present their proposals.
The input of the Steering Committee would then be taken in consideration
when selecting the successful bidder.
·
Mr. Simms requested
that any specific comments on the revised Scope of Work document be emailed to
him at fmsimms@aep.com within 10 days of
the date of the meeting. The next step
is for AEP to finalize the document and begin the bidding process.
The meeting concluded at approximately 2:00 p.m. (EDT).
Smtnsteermt2notes